LEVELLING IN SURVEYING
Leveling is an operation in surveying performed to determine the difference in levels of two points. By this operation the height of a point from a datum, known as elevation, is determined.
LEVEL SURFACE
A level
surface is the equipotential surface of the earth’s gravity field. It is a
curved surface and
every
element of which is normal to the plumb line.
DATUM
A datum
is a reference surface of constant potential, called as a level surface of
the earth’s gravity field, for measuring the elevations of the points. One of
such surfaces is the mean sea level surface and is considered as a standard
datum. Also an arbitrary surface may be adopted as a datum.
LEVEL LINE
A line
lying in a level surface is a level line. It is thus a curved line.
A
level in proper adjustment, and correctly set up, produces a horizontal line of
sight which
is at right angles to the direction of gravity and tangential to the level line at the instrument height. It follows a constant height above mean sea level and hence is a curved line, as shown in Fig. 3.1. Over short distances, such as those met in civil engineering works, the two lines can be taken to coincide. Over long distances a correction is required to reduce the staff readings given by the horizontal line of sight to the level line equivalent. Refraction of the line of sight is also to be taken into account. The corrections for the curvature of the level line Cc and refraction Cr are shown in
DIRECT
DIFFERENTIAL OR SPIRIT LEVELLING
Differential
leveling or spirit leveling is the most accurate simple direct method of
determining the difference of level between two points using an instrument
known as level with a leveling staff.
A
level establishes a horizontal line of sight and the difference in the level of
the line of sight and
the
point over which the levelling staff is held, is measured through the levelling
staff. Fig. 3.3 shows the principle of determining the difference in level Äh between two points A and B, and thus the elevation
of one of them can be determined if the elevation of the other one is known. SA
and SB are the staff readings at A and B,
respectively, and hA and hB are their respective elevations.
(i)
if SB < SA, the point B is higher than point A.
(ii)
if SB > SA, the point B is lower than point A.
(iii)
to determine the difference of level, the elevation of ground point at which
the level is
set
up, is not required.
Booking
and Reducing the Levels
Before
discussing the booking and methods of reducing levels, the following terms
associated with differential leveling must be understood.
Station:
A station is the point where the leveling staff is held. (Points
A, a, b, B, c, and C
in
Fig. 3.4).
Height
of instrument (H.I.) or height of collimation: For any set up of the level, the
elevation
of the line of sight is the height of instrument. (H.I. = hA + SA in
Fig. 3.3).
Back
sight (B.S.): It is the first reading
taken on the staff after setting up the level usually
to
determine the height of instrument. It is usually made to some form of a bench
mark (B.M.) or
to
the points whose elevations have already been determined. When the instrument
position has to be changed, the first sight taken in the next section is also a
back sight. (Staff readings S1 and S5
Fore
sight (F.S.): It is the last reading
from an instrument position on to a staff held at a point.
It
is thus the last reading taken within a section of levels before shifting the
instrument to the next
section,
and also the last reading taken over the whole series of levels. (Staff
readings S4 and S7
in
Fig. 3.4).
Change
point (C.P.) or turning point: A change
point or turning point is the point where
both
the fore sight and back sight are made on a staff held at that point. A change
point is required before moving the level from one section to another section.
By taking the fore sight the elevation of the change point is determined and by
taking the back sight the height of instrument is determined.
The
change points relate the various sections by making fore sight and back sight
at the same point. (Point B in Fig. 3.4).
Intermediate
sight (I.S.): The term ‘intermediate
sight’ covers all sightings and consequent
staff
readings made between back sight and fore sight within each section. Thus,
intermediate sight station is neither the change point nor the last point.
(Points a, b, and c in Fig. 3.4).
Balancing
of sights: When the distances of the
stations where back sight and fore sight are
taken
from the instrument station, are kept approximately equal, it is known as
balancing of sights. Balancing of sights minimizes the effect of instrumental
and other errors.
Reduced
level (R.L.): Reduced level of a point is its height or depth above or below
the
assumed datum. It
is the elevation of the point.
Rise
and fall: The difference of level between two
consecutive points indicates a rise or a
fall
between the two points. In Fig. 3.3, if (SA – SB) is positive, it is a
rise and if negative, it is
a
fall. Rise and fall are determined for the points lying within a section.
Section:
A section comprises of one back sight, one fore sight and all
the intermediate sights
taken
from one instrument set up within that section. Thus the number of sections is
equal to the
number
of set ups of the instrument. (From A to B for instrument
position 1 is section-1 and from
B to C for instrument position 2 is section-2 in Fig. 3.4). For booking and reducing the levels of points, there are two systems, namely the height of instrument or height of collimation method and rise and fall method. The columns for booking the readings in a level book are same for both the methods but for reducing the levels, the number of additional columns depends upon the method of reducing the levels.
Note
that except for the change point, each staff reading is written on a separate
line so that each staff position has its unique reduced level. This remains true
at the change point since the staff does not move and the back sight from a
forward instrument station is taken at the same staff position where the fore
sight has been taken from the backward instrument station.
To explain the booking and reducing levels, the levelling operation from stations A to C shown in Fig. 3.4, has been presented in Tables 3.1 and 3.2 for both the methods. These tables may have additional columns for showing chainage, embankment, cutting, etc., if required
In
reducing the levels for various points by the height of instrument method, the
height of
instrument
(H.I.) for the each section highlighted by different shades, is determined by
adding the elevation of the point to the back sight reading taken at that point.
The H.I. remains unchanged for all the staff readings taken within that section
and therefore, the levels of all the points lying in that section are reduced
by subtracting the corresponding staff readings, i.e., I.S. or F.S., from the
H.I. of that section.
In
the rise and fall method, the rises and the falls are found out for the points
lying within
each
section. Adding or subtracting the rise or fall to or from the reduced level of
the backward
The
arithmetic involved in reduction of the levels is used as check on the
computations. The
following
rules are used in the two methods of reduction of levels.
(a)
For the height of instrument method
(i)
Ó B.S.
– Ó F.S.
= Last R.L. – First R.L.
(ii)
Ó [H.I.
. (No.
of I.S.’s + 1)] – Ó I.S. – Ó F.S. = Ó R.L. – First R.L.
(b)
For the rise and fall method
Ó B.S. – Ó F.S. = Ó Rise – Ó Fall = Last R.L. – First R.
COMPARISON
OF METHODS AND THEIR USES
Less
arithmetic is involved in the reduction of levels with the height of instrument
method than with the rise and fall method, in particular when large numbers of
intermediate sights is involved. Moreover, the rise and fall method gives an
arithmetic check on all the levels reduced, i.e., including the points where
the intermediate sights have been taken, whereas in the height of instrument method,
the check is on the levels reduced at the change points only. In the height of
instrument method the check on all the sights is available only using the
second formula that is not as simple as the first one.
The
height of instrument method involves less computation in reducing the levels
when there
are
large numbers of intermediate sights and thus it is faster than the rise and
fall method.
The
rise and fall method, therefore, should be employed only when a very few or no
intermediate sights are taken in the whole leveling operation. In such case,
frequent change of instrument position requires determination of the height of
instrument for the each setting of the instrument and, therefore, computations
involved in the height of instrument method may be more or less equal to that
required in the rise and fall method. On the other hand, it has a disadvantage
of not having check on the intermediate sights, if any, unless the second check
is applied.

0 Comments
19